December 9, 2009

7th Week Starting Lock Up Stage

We nearly at Lock Up Stage hopefully by some stage next week.

The brickies are nearly done there just waiting for the roof people to finish up as they are holding up the brickies with there safety railing.

I also ran yellow tongue stripping today, may have gotten a little to excited as I ran it everywhere, as who knows how many times will change our minds on where to run the extra cables for after hand over.






Posted by Picasa

1 comment:

  1. Are you just going to leave the yellow tongue in the walls for pulling through cables later? I was thinking of just running my own cables in the frame once the electrician is done (and obviously before plaster goes up!). But a good idea anyway, I think I'll also put in some yellow tongue in case future wires need to be pulled!

    ReplyDelete